F.No.8-25/2017-18/Fin
Government of India
Department of Telecommunications
Sanchar Bhawan, ZO-Ashoka Road, New Delhi-110001
(Finance Section)

Dated: 28th December, 2017

Subject: Economy Measures- Mandatory installation of LED based lighting in Government Buildings.
economy-measures-mandatory-installation-led-dot-om-paramnews

Find enclosed herewith OM No. 25(24)/E.Coord/2017 dated 01.12.2017 issued by Ministry of Finance, Department of Expenditure on the subject cited above for compliance.

This issues with the approval of Competent Authority.

R.C. Kumar
Asst. Director General (Finance)
Tel: 011l-23036290

Copy to:-
1. The Wireless Advisor, DoT HQ
2. The Additional Setretary (T)
3. The Administrator, USOF, DoT HQ
4. All Sr. DDsG/DDsG/JS(A)/JS(T) in DoT HQ
5. Sr. DDG (TERM)-to inform all field units.
6. Sr. DDG (TEC)/NTIPRIT/DG (NICF)
7. All Pr. CCA/CCA

Copy for information:

1. Sr. PPS to Secretary (T)
2. PPS to Member (F) /Member (T)/Member (S)
3. PPS to Advisor (F)
4. ‘ PPS to Administrator (USOF)/AS(T)
5. US (SEA-II)-(Scanned copy already e-mailed at neha.singh76@nic.in).

__________________________________________________________________________________________________________________________________________________________________

Most Immediate

No.25(24)lE.Coord/2017
Government of India
Ministry of Finance
Department of Expenditure

North Block, New Delhi
Dated: 01 December, 2017

OFFICE MEMORANDUM

Subject: Economy Measures- Mandatory installation of LED based Iightings in Government Buildings- reg.

Reference is invited to this Department’s OM of even number dated 04.08.2017 wherein all Ministries/Departments were requested to convert the existing’ lightings/equipments into LED based lightings and energy efficient equipments on priority utilizing the services of CPWD/EESL. The model Agreement/Contract to be entered in' to between the Client Ministry/Department and EESL was also circulated.

2. Recently, the implementation progress of LED based Iightings was reviewed by Group of Officers vide meeting; in Cabinet Secretariat on 07.11.2017. During deliberations, some of- the Ministries/Departments informed about the time taken in obtaining administrative approvals and financial concurrence. 

3. The mandatory installation of LED based lightings in Government buildings is a time bound activity. Hence, it is requested of all Financial Advisors to facilitate expeditious processing of the LED based lighting installation proposals received in their Divisions.

(Annie G Mathew)
Joint Secretary (Pers.)
Tel.:2309 3283

To:
All Fiancial Advisors of Ministries/Departments

Copy to:
Cabinet Secretariat [ Shri. S.A.M. Rizvi, Joint Secretary ]